Weddington Water Tower

Posted by Melody Friday, December 18, 2015 10:59:00 AM

UCPW has announced that the new water tower on Hemby Rd. is on track for completion in May 2016.  The project, which features a 1.5 million gallon, 170' tall elevated water tank, will provide more consistent, sustainable water pressure for customers in the Marvin and Weddington areas.  Construction on the tower's water main piping, foundation and concrete shaft have been completed.  The water tank is constructed and was raised on Dec. 4.  It will become fully operational when the new booster pump station station located on Providence Rd. is completed in May.  Once completed, UCPW customers can expect to see a noticeable difference in your home's water pressure.  